The steel structure building area of the new plant area project is 48000 square meters, and the main steel structure is about 2100 tons. The materials of the first block will be mobilized for construction on July 15, 2020. By October 15, 2020, all the installation of the project will be completed, which will last 90 days and be completed 10 days in advance.